Launch2¶
Timeline¶
Saturday, March 17
The launch
- 7:30 Team meets, eats breakfast. Discovered that the smartphone did not charge.
- 8:15 Load truck, moved to hanger
- 9:30 Ragnar Rafn Eðvaldsson begins running down the checklist.
- 9:35 Sverrir Haraldsson finishes filling the balloon
- 10:55 Vikar Hlynur Þórisson attaches all the GoPro Cameras
- 11:10 Electronics are turned on and sealed into box. Niklas Joel Meier turns on the logger and failsafe.
- 11:16 Kristjan Kristján Gerhard Karlsson Grimm gets launch clearance
- 11:25 Balloon launch from Reykjavik University
- 12:57 Balloon popped at 34000 altitude. (APRS did not capture exact)
- 13:25 Crash at Coordinates N64.37315, W19.24017 from SPOT
- 13:46 Þórður Sigurbjartsson, Arní from CCP, meet with NORSK Rescue Helicopter at RVK airport (we watched from U215)
- 14:19 Heli takes off
- 17:00 Heli returns, unsuccessful
- 17:30 Debrief with pizza
- 19:00 Discover possible issue, GPS coordinates in wrong format for helicopter. Plans for recovery tomorrow.
Sunday, March 18
Skyward sword to the rescue, led by Páll Pálsson
- 5:00 Planned to head out
- 9:45 Last transmission of the SPOT
- ?? One superjeep gets broken driveshaft, has to be repaired
- ?? Many attempts to follow road require detours and very slow progress.
- 12:30 Snow becomes bad?
- 13:50 Arrival at location