h1. Launch2 

 h2. Timeline 

 Saturday, March 17 

 The launch 

 * 7:30 Team meets, eats breakfast.    Discovered that the smartphone did not charge. 
 * 8:15 Load truck, moved to hanger 
 * 9:30 Ragnar Rafn Eðvaldsson begins running down the checklist. 
 * 9:35 Sverrir Haraldsson finishes filling the balloon 
 * 10:55 Vikar Hlynur Þórisson attaches all the GoPro Cameras 
 * 11:10 Electronics are turned on and sealed into box.    Niklas Joel Meier turns on the logger and failsafe. 
 * 11:16 Kristjan Kristján Gerhard Karlsson Grimm gets launch clearance 
 * 11:25 Balloon launch from Reykjavik University 
 * 12:57 Balloon popped at 34000 altitude.    (APRS did not capture exact) 
 * 13:25 Crash at Coordinates N64.37315, W19.24017 from SPOT 
 * 13:46 Þórður Sigurbjartsson, Arní from CCP, meet with NORSK Rescue Helicopter at RVK airport (we watched from U215) 
 * 14:19 Heli takes off 
 * 17:00 Heli returns, unsuccessful 
 * 17:30 Debrief with pizza 
 * 19:00 Discover possible issue, GPS coordinates in wrong format for helicopter.    Plans for recovery tomorrow. 

 Sunday, March 18 

 Skyward sword to the rescue, led by Páll Pálsson 

 * 5:00 Planned to head out 
 * 9:45 Last transmission of the SPOT 
 * ?? One superjeep gets broken driveshaft, has to be repaired 
 * ?? Many attempts to follow road require detours and very slow progress. 
 * 12:30 Snow becomes bad? 
 * 13:50 Arrival at location