Risk Analysis » History » Version 1

Joseph Foley, 2012-03-15 13:46
documented the current risk assessment chart

1 1 Joseph Foley
h1. Risk Analysis
2
3
* T = Technical
4
* L = Logistical
5
* F = Financial
6
7
Second numbers is the [liklyness, impact]
8
9
h2. Preparation
10
11
* T1 Cutoff too early [1,5]
12
* T2 Cutoff too late [3,3]
13
* T3 Weight increase from environment [3,2]
14
* T4 Strings fail (knots) [2,5]
15
* T5 Ascend rate too slow [2,4]
16
* T6 Ascend rate too fast [1,1]
17
* T7 Trackuino turns off [2,3]
18
* T8 Spot stops transmitting [1,4]
19
* T9 Cameras stop recording [1,5]
20
21
h2. Flight
22
23
* T1 Forget tool needed [2,2]
24
* T2 Forget parts [2,2]
25
* T3 Prototype not ready [3,5]
26
* T4 Balloon pops in hanger [2,4]
27
* L5 Balloon cannot fit out door [2,2]
28
* L6 Dead batteries or forget to charge [1,6]
29
* L7 Forget or bad heaters [2,3]