| 1 | 1 | Joseph Foley | h1. Flight 3 |
|---|---|---|---|
| 2 | |||
| 3 | h2. Timeline |
||
| 4 | |||
| 5 | * 9:00 Most have arrived at CCP and are eating breakfast |
||
| 6 | * 9:30 the team arrives at hofro (Naval Research) to prepare the launcy |
||
| 7 | * 9:45 baloon assembly begins |
||
| 8 | * 10:00 cut down wire in place at the top of parachute |
||
| 9 | * 10:15 cut down wire being put into the foam box |
||
| 10 | * 10:20 Ragnar fucking [sic] about with ropes |
||
| 11 | * 10:25 Space ship hung up on the device |
||
| 12 | * 10:30 CCP start the desktop live stream! |
||
| 13 | * 10:35 Small red HR balloon released to see general wind direction |
||
| 14 | * 10:45 trying to get a signal from the Spot GPS tracker |
||
| 15 | * 10:50 camera in foam boxes being mounted |
||
| 16 | * 11:00 balloon filling process started! Takes about 22 minutes. |
||
| 17 | * 11:15 Helium flowing into balloon |
||
| 18 | * 11:53 Kristjan calls the tower |
||
| 19 | * 11:55 Box sealed, trackers checked. Spot at 11:22 |
||
| 20 | * 12:03 Cameras on |
||
| 21 | * 12:19 Authority 1 approves, other asks for more information: ascent, heading. Vikar has to reset the cutoff |
||
| 22 | * 12:23 Given the go ahead! |
||
| 23 | |||
| 24 | Notes by Halldor, transcribed by Joe. |